Campus Expansion

at Brigham and Women's Faulkner Hospital

BWFH's Campus Expansion

Brigham and Women’s Faulkner Hospital received approval for the Determination of Need (DoN) submission in May 2022 to begin working on a campus expansion program to better support care in our communities. Construction began in May of 2023. 

We welcome your feedback! Contact us at cdelaney5@mgb.org.


Construction Update: September 30 to October 11, 2024

Third-Floor Hillside Garage

Final site grading and sidewalk construction is underway, as well as interior work. The fall phase of landscaping work has also begun with the placement of loam and tree planting.

Inpatient Addition

Work is progressing for the inpatient addition with interior work and exterior wall installation ongoing. Staff and patients should expect intermittent disruptions to the loop road during this time.

Street Enhancements

Repaving of Allandale and Centre Street is expected to be complete by Friday, October 4. This work will impact the section of Allandale Street between the Springhouse entry driveway and Centre Street. The Centre Street/Allandale Street intersection will also be paved. Per the request of the Department of Conservation and Recreation (DCR) and the Boston Transportation Department, milling and paving the road was scheduled to take place during the evening from 8 p.m. to 4 a.m. on Friday, October 4. This work has been postponed due to unrelated work by National Grid in the area. All other road work will be done during the day, between 9 a.m. and 3 p.m. Striping of Centre and Allandale Streets, including the intersection on Whitcomb Avenue and Centre Street, is scheduled to happen on Tuesday, October 8, from 8 p.m. to 4 a.m. Please note, these dates are subject to change in the event of inclement weather or unforeseen conditions. Evening work will cause some noise disruptions and roads will have additional illumination. All work will require partial lane closures. Police details will be in place to direct the flow of traffic.

Interior and Roof

Work is also underway inside the hospital and on the roof to accommodate the new inpatient addition. During this time, expect there will be increased noise and possible disturbances within the hospital. Individual departments that will be directly impacted will be notified in advance to allow them to prepare and mitigate any possible disruptions to operations.

Please note, the corridor outside of Huvos Auditorium is temporarily closed. The ATM located there will has been temporarily relocated to the main hallway across from the vending machines. On Monday, September 30, the existing Cafeteria seating area will close and the new dining room will open, pending the approval of a temporary certificate of occupancy.