Brigham and Women’s Faulkner Hospital received approval for the Determination of Need (DoN) submission in May 2022 to begin working on a campus expansion program to better support care in our communities. Construction began in May of 2023.
We welcome your feedback! Contact us at cdelaney5@mgb.org.
Construction Update: Jan. 6–17, 2025
Garage
· Miscellaneous work being completed at new garage.
· Jan. 6: Mobilize site fence to prepare for old garage abatement and demolition. Road in front of old garage will be limited to one lane.
· Jan. 13: Abatement of old garage begins.
· Old garage demolition to begin in late February.
Inpatient Addition
Work is progressing for the inpatient addition. Please see the following updates for work taking place within hospital spaces:
First-floor Radiology active spaces:
Shutdown of Radiology east corridor, phase 1, Monday–Friday, 8 p.m.–6 a.m. Access to IN/IR control room and Trophon room will be maintained.
MRI/staff lounge renovations will continue.
Second-floor Radiology active spaces:
Mechanical room (north --- future fire pump room), fire pump room construction ongoing.
Continued use of hospital loading dock.
Third-floor Cafeteria:
Construction of the existing seating area and office renovation continues with ceramic tiles and drywall installation.
Fourth and fifth floors:
Taping and sanding of drywall and painting walls for the new spaces.
Exterior site work
Exterior wall closure at MRI opening.
Wiring of exterior signage.
Atrium garage bike storage, week of Jan. 13
Interior work within inpatient additions
First Floor: MEP finishes/flooring
Second Floor: MEP finishes and above ceiling punch list
Third, Fourth and Fifth Floors: Cleaning, wall protection and millwork
MEP work on all floors
Mechanical Penthouse flooring
Future work
The flooring in the corridor outside Physical Therapy/Occupational Therapy will be replaced the weekend of Jan. 18, 2025.
Fire pump sprinkler shutdown is planned for Saturday, Jan. 18, and Saturday, Jan. 25 (coordinated with Boston Fire Department).