Brigham and Women’s Faulkner Hospital received approval for the Determination of Need (DoN) submission in May 2022 to begin working on a campus expansion program to better support care in our communities. Construction began in May of 2023.
We welcome your feedback! Contact us at cdelaney5@mgb.org.
Construction Update: Nov. 11–22, 2024
Hillside Garage
The site fence is scheduled to be removed. The building will remain locked and fence panels will be installed at new garage entrances. Caulking of canopies and entrance signs will also take place.
Inside the garage, crews are finishing painting, installing pipe guards and reviewing a punch list of remaining items that need attention.
Loop Road
Beginning Nov. 12, crews will begin a repaving operation on the loop road. Police details will be provided on-site to assist with traffic management. Full depth removal and binder coat will occur between 8 a.m. and 2:30 p.m. The final overlay coat and line striping will happen at night. The line stripe is expected to be completed on Nov. 29. Staff and patients should use Whitcomb when exiting during loop road paving – thank you.
Upcoming work
- January 2025: Demolition of the
existing garage begins.
Inpatient Addition
Work is progressing for the inpatient addition. Please see the following updates for work taking place within hospital spaces from Nov. 11–22:
First-floor Radiology active spaces:
- Shutdown of Radiology east
corridor, phase 1, Monday–Friday, 8 p.m.–6 a.m. Access to IN/IR control
room and Trophon room will be maintained.
- Nov. 12: MRI/staff lounge
renovation begins.
Second-floor Radiology active spaces:
- Mechanical room (north ---
future fire pump room), fire pump room construction ongoing.
- Plastics office and café
storage demolition and renovations.
- Continued use of hospital
loading dock.
Interior work within inpatient addition:
- First floor: Flooring and
ceiling grid
- Second floor: Painting, ceiling
grid flooring
- Third, fourth and fifth floors:
interior finishes
- Mechanical, electrical and
plumbing work on all floors
- Mechanical penthouse cleanup
Exterior site work
- On Nov. 2, removal of the
electrical vault/transformer will take place. A crane will be set up in
the loop road and require a full road closure from 8 a.m. to noon.
- Exterior wall infill at the
temporary loading dock
- Granite curb install
- Fuel oil tank piping and
backfill
- Roof protection and stair tower
removal
Cafeteria
- Construction of the existing
seating area continues (third floor).
- Framing for the new spaces and
rough mechanical, electrical and plumbing engineering begins (fourth and
fifth floors).