Campus Expansion

at Brigham and Women's Faulkner Hospital

BWFH's Campus Expansion

Brigham and Women’s Faulkner Hospital received approval for the Determination of Need (DoN) submission in May 2022 to begin working on a campus expansion program to better support care in our communities. Construction began in May of 2023.

We welcome your feedback! Contact us at cdelaney5@mgb.org.


Construction Update: Nov. 11–22, 2024

Hillside Garage

The site fence is scheduled to be removed. The building will remain locked and fence panels will be installed at new garage entrances. Caulking of canopies and entrance signs will also take place.

Inside the garage, crews are finishing painting, installing pipe guards and reviewing a punch list of remaining items that need attention.

Loop Road

Beginning Nov. 12, crews will begin a repaving operation on the loop road. Police details will be provided on-site to assist with traffic management. Full depth removal and binder coat will occur between 8 a.m. and 2:30 p.m. The final overlay coat and line striping will happen at night. The line stripe is expected to be completed on Nov. 29. Staff and patients should use Whitcomb when exiting during loop road paving – thank you.

Upcoming work

  • January 2025: Demolition of the existing garage begins.

Inpatient Addition

Work is progressing for the inpatient addition. Please see the following updates for work taking place within hospital spaces from Nov. 11–22:

First-floor Radiology active spaces:

  • Shutdown of Radiology east corridor, phase 1, Monday–Friday, 8 p.m.–6 a.m. Access to IN/IR control room and Trophon room will be maintained.
  • Nov. 12: MRI/staff lounge renovation begins.

Second-floor Radiology active spaces:

  • Mechanical room (north --- future fire pump room), fire pump room construction ongoing.
  • Plastics office and café storage demolition and renovations.
  • Continued use of hospital loading dock.

Interior work within inpatient addition:

  • First floor: Flooring and ceiling grid
  • Second floor: Painting, ceiling grid flooring
  • Third, fourth and fifth floors: interior finishes
  • Mechanical, electrical and plumbing work on all floors
  • Mechanical penthouse cleanup

Exterior site work

  • On Nov. 2, removal of the electrical vault/transformer will take place. A crane will be set up in the loop road and require a full road closure from 8 a.m. to noon.
  • Exterior wall infill at the temporary loading dock
  • Granite curb install
  • Fuel oil tank piping and backfill
  • Roof protection and stair tower removal

Cafeteria

  • Construction of the existing seating area continues (third floor).
  • Framing for the new spaces and rough mechanical, electrical and plumbing engineering begins (fourth and fifth floors).