Campus Expansion

at Brigham and Women's Faulkner Hospital

BWFH's Campus Expansion

Brigham and Women’s Faulkner Hospital received approval for the Determination of Need (DoN) submission in May 2022 to begin working on a campus expansion program to better support care in our communities. Construction began in May of 2023.

We welcome your feedback! Contact us at cdelaney5@mgb.org.


Construction Update: April 22–May 2, 2025

Garage

  • Monday, 4/28: Anticipated old garage demolition following Boston Landmarks Commission’s approval on Friday, 4/18. Pending permit approval. Further updates to come.
  • Installation of Distributed Antenna System (DAS) to improve cell coverage.

Inpatient Addition

Work Within Hospital Spaces

  • 2nd Floor
    • Continued use of Hospital Loading Dock.
    • Furniture deliveries continue through April.

Exterior Site Work

  • April – May: Landscaping and curbing at new entry.
  • 4/22 – 5/2: Temporary sidewalk removal.
  • Week of 5/5: Construction fence removal, curbing for the island in front of the main entrance to be completed.

Interior Work Within Inpatient Addition

  • 1st floor – 5th floor: Final clean and punch list.
  • 2nd floor – 5th floor: OFCI install.